Task
|
Procedure
|
Assign a schedule to an activity
|
-
Double-click an activity and click the Task page in the Properties dialog box.
-
On the Step tab, select the Limited Schedule check box and select a schedule.
|
Assign a schedule to a resource
|
-
On the Model toolbar, click the tool. or On the Model menu, choose Resources.
-
In the Define Resources dialog box, select a resource from the list on the left.
-
On the Properties tab, set a schedule.
|
Assign a schedule to a generator
|
-
On the Model toolbar, click the tool. or On the Model menu, choose Generators.
-
In the Generators dialog box, select the Limited Schedule check box and select a schedule from the list.
|