Home > Simulation Environment Procedures > Calendars > Assign Schedules

Assign Schedules

Task

Procedure

Assign a schedule to an activity

  1. Double-click an activity and click the Task page in the Properties dialog box.

  2. On the Step tab, select the Limited Schedule check box and select a schedule.

Assign a schedule to a resource

  1. On the Model toolbar, click the model_resources.bmp tool.
    or
    On the Model menu, choose Resources.

  2. In the Define Resources dialog box, select a resource from the list on the left.

  3. On the Properties tab, set a schedule.

Assign a schedule to a generator

  1. On the Model toolbar, click the generatorbutton00006.bmp tool.
    or
    On the Model menu, choose Generators.

  2. In the Generators dialog box, select the Limited Schedule check box and select a schedule from the list.

Related Topics

Simulation Environment Procedures

Events

Overview Topics

Schedules, Composite Schedules, and Overtime